Purchase Requisition Activities

336
 PR # Date Description Items Orders Pending? Pending Text
2402002183 04.10.2024 SWITCH,PUSH BUTTON AND INDICATION LAMPS  23  1
Id Date Activity Remarks
93 25.11.2024 037b posted in SRM on 25-Nov-2024.
2402002144 01.10.2024 TERMINAL BAR FOR SLIPRING INDUCTION MOTOR 355S8  1  1
Id Date Activity Remarks
81 28.10.2024 Technical Recommendation posted in SRM. To be approved by HOD. RFx # 2000004079
2402002049 21.09.2024 FIRING MODULE AND ARMATURE COIL ASSEMBLY FOR LHF OF CCM-I  2  1
Id Date Activity Remarks
82 01.11.2024 Technical recommendation (037b) raised in SRM and approved by I/O. (RFx : 2000003989) To be approved by HOD.
83 01.11.2024 Technical recommendation approved by HOD (in SRM).
2402001943 11.09.2024 SLIPRING INDUCTION MOTOR 200L6 FOR CRANES (2 EA)  1  1
Id Date Activity Remarks
119 27.02.2025 Amendment to PO-Deliver prepone to 28-Feb-2025.
78 22.10.2024 037b posted in SRM and approved by HOD. Informed MM/MJ through mail.
2402001887 07.09.2024 ELECTROHYDRAULIC THRUSTOR 185KG FOR EOT CRANES  1  1
Id Date Activity Remarks
75 07.10.2024 Technical recommendation initiated and released by I/O in SRM. Pending for approval of the HOD.
71 23.09.2024 Replied to email of ms Swagatika Behera (MJ) and suggested LTE thro' SRM. OTE thro' GEM was suggested as per the last PR.
2402001674 16.08.2024 SQ. CAGE INDUCTION MOTOR FOR SLAG DUMPING CAR  1  1
Id Date Activity Remarks
108 14.01.2025 GAD and MDS approved and sent to the vendor M/s Apex Trading Co
2402001612 08.08.2024 SLIPRING INDUCTION MOTOR 355L10 FOR CRANE 235 OF CCM-I  1  1
Id Date Activity Remarks
58 25.08.2024 Replied to the query of CGM(E) regarding Acceptable Makes. Query was given by CGM(E) to justify Acceptable Makes in Special Terms of the PR. Replied.
55 12.08.2024 Release initiated after allocation of MSP budget for 2025-26.
2402001563 05.08.2024 SQ CAGE INDUCTION MOTOR 280M4 FOR QUENCHER PUMP  1  1
Id Date Activity Remarks
107 11.01.2025 Representation of New Age Centre examined in GEM and found OK. Replied to MJ. Representation of M/s New Age Trade Centre examined and found OK.
2402001490 31.07.2024 INSULATOR FOR CRANE CURRENT COLLECTOR (400 EA)  1  1
Id Date Activity Remarks
70 23.09.2024 037b posted by I/O in SRM on 23/09/2024
2402001396 23.07.2024 CARBON BRUSHES FOR MOTORS  5  1
Id Date Activity Remarks
64 05.09.2024 Suggested MJ to exclude vendors through email, which are not registered in SRM.
2402001000 21.06.2024 SPARES FOR CRANE 226 WEIGHING SYSTEM  7  1
Id Date Activity Remarks
84 05.11.2024 Technical recommendation posted in GEM and eNote initiated.
66 19.09.2024 Replied to Convenor (GM, MSS) regarding delivery after getting confirmation from M/s ABB. M/s ABB confirmed to supply within March-2025 if PO is placed within Dec-2024.
51 07.08.2024 Estimate revised for Item-1 and 3 as per TA to CGM I/c (E&P) Estimate revised for Item-1 and 3 as per TA to CGM I/c (E&P)-LPP considered.
2402000892 10.06.2024 SLIPRING INDUCTION MOTOR 180L6  1  1
Id Date Activity Remarks
59 30.08.2024 Drawings for 180L6 received from M/s Wheel Board thro' mail. Approved and replied. PO on M/s Wheel Board & Co.
53 09.08.2024 037b posted in SRM and note initiated on 09/08/2024.
2402000869 10.06.2024 SPARES FOR CASTER PLC (Schneider)  8  1
Id Date Activity Remarks
63 05.09.2024 037b posted in SRM and eNote initiated.
2402000372 27.04.2024 FAN, PUSH BUTTON AND MCB BOX  6  2 Cable Tray and one fan rejected. RPN action taken.
Id Date Activity Remarks
31 12.06.2024 037b posted in SRM on with HOD approval.
2402000248 22.04.2024 WEB-BASED PLANNING MANAGEMENT SYSTEM  1  1
Id Date Activity Remarks
37 24.06.2024 Technical recommendation posted in GEM and eNote initiated.
27 30.05.2024 Discussed with Mr Biswajit Sahoo (GM, MM-P) and Mr Uday Anand (MJ) regarding the requirement.
2402000057 08.04.2024 WEIGHING CONTROLLER FOR CONVERTERS  1  1
No Activity against this PR entered so far. Click here to add one.
2402000021 02.04.2024 HT MOTOR 750KW FOR GCP ID FAN 5  1  1
Id Date Activity Remarks
60 30.08.2024 Drawings received from M/s Wheel Board for approval.
61 30.08.2024 eNote moved for amendment as requested by the vendor for Test Certificate clause. Material Test Certificate in Documents Required by Consignee to be replaced with Manufacturing Test Certificate.
56 12.08.2024 MSP budget received for 2025-26 to release the PO. Intimated to Mr S. Ghosh
49 30.07.2024 Mail received from Mr Omkar Mohanty regarding GEM error. Buyer (Santanu Ghosh) is unable to place order in GEM.
44 18.07.2024 Technical recommendation posted in GEM and eNote moved.
33 13.06.2024 Unblocked for release (> 45 days) by giving mail to G. Arora. Then released by CGM I/c (E&P).
34 13.06.2024 Reply given to GM MM-P Mr B. Sahu in eNote to process the case.
32 12.06.2024 PR dereleased (Chairman-CGM I/c E&P). Drawing clause to be added in Special Terms PR is not editable. ERP team to be contacted.
26 30.05.2024 WO No. 9000099871 forwarded to Design deptt HOD as per MM-Purchase.
2402000001 02.04.2024 POWER CONTACTORS (80A, 110A, 185A, 265A)  4  1
No Activity against this PR entered so far. Click here to add one.
2390000063 05.09.2023 AUTOMATION OF LD BY IO EXTENSION OF GCP PLC SYSTEM (AMR)  1  1
No Activity against this PR entered so far. Click here to add one.
2369000022 18.05.2023 CABLES FOR SMS-I  2  0
No Activity against this PR entered so far. Click here to add one.